Demolition of Needles Operation Yard Project - $477,483.00 |
| The demolition of the operation yard project in Needles, CA consisted of razing and disposal of three existing buildings, including the floor slabs, foundations, concrete aprons surrounding the area, and grading the area to match the landscape. |
Additional work features included:Removal and disposal of asbestos and lead paint. Results Achieved:- Successful removal and disposal of asbestos and lead paint
- Remote site operations
- Improvement of 4.8 acres of federal property that was in disrepair and vandalized
- Elimination of substandard facilities
- 100% accident free, safety program goals met
- On time completion
|
|
|
Demolition of Buildings 176 and 327 - $1,160,880.00 |
| The demolition of Buildings 176 & 327 at the Marine Corps Logistics Base in Barstow, California included structural demolition and capping of all above and below ground utilities, removal of concrete slabs, stem walls, footings and foundation work, and removal of underground electrical lines. |
Additional work features included:Removal of boilers, chillers and HVAC equipment, fire protections systems, emergency generators and all piping systems, and site restoration including dirt fill and compaction to achieve original ground characteristics. Results Achieved:- Elimination of substandard facilities
- Recycling of crushed concrete to fill in the basement of the boiler building
- Removal of 3 story surplus and outdated buildings
- 100% accident free, safety program goals met
- On time completion
|
|
|