Aerospace AFP Foundation

HHCI furnished, placed and compacted aggregate base-rock under all new slabs /foundation for the AFP Foundation. For this project, the existing concreted was sawed and removed, then excavated per the required depths. HHCI furnished and installed steel forms with I-Beam support structure, then poured, finished, and striped the structural concrete foundation.

Key Work Features

  • Sawcut and removed 30 CY of existing concrete
  • Excavated 300 CY with Tier IV Diesel Equipment
  • Exposed Sub-Grade and statically compacted 90% relative density
  • Furnished, placed, and compacted aggregate base-rock under all new slabs / foundations
  • Furnished and installed reinforcing bars throughout AFP foundation
  • Furnished and installed HEB & IPN beams
  • Furnished and installed electrical service to AFP, tilt table, security fence, and control desk

Results

  • 100% accident-free operations
  • Project Completed ahead of schedul