Plant F63R Construction of the Recycled Water Plant Improvements

For the Recycled Water Plant Improvements, HHCI’s team completed the construction of the booster station pipelines, drainage piping & structures, and the concrete building for Plant F63R located in Fontana, CA. As part of the site improvements, our team successfully installed the following: potable water backup supply piping; utility vault and water meter; fire hydrant and guard posts; pressure sustaining valve; and booster pump cans and associated concrete column.

Key Work Features

  • Demolition
  • Earthwork
  • Piping
  • Booster station building
  • Electrical
  • Site improvements

Results

  • Project was completed with over 4,712 safety man-hours
Plant-F63-2
Plant-F63-1
Plant-F63-4
Plant-F63-3